This week our volunteers started working on the porch railing, hung the shudders, installed the door hardware on the interior doors, and laid luan under-layment down throughout the house where the vinyl flooring will go in. Our subcontractors poured the driveway, porches and walkway. Our HVAC subcontractor put in their equipment and vent covers.
Next week, we expect to have the vinyl laid, plumbing final, and our sponsors, the First Settlers Region Porsche Club will have their last sponsored build where they will be putting in the landscaping in addition to building a shed. We’re almost done. Our home buyer Cecilia will close on the house in mid March. Look for information on her home dedication at the end of March.
Follow the progress and see who has been volunteering daily on our Facebook
Comments