| Date | Scheduled Work |
|---|---|
| Wed 8/22 | Complete porches. Complete Shed trim. Rough grade gardens. Complete interior trim out. Install stair trim and bannisters. |
| Thurs 8/23 | Pour driveway. Install gutters |
| Sat 8/25 | Final check for tasks before final |
| Mon 8/27 | Turn over for final inspection. |
| September 1 | Wand moves in ... we hope! |